Tolls to cross the I-5 Bridge could start in summer 2028 at $1.55 to $3.90 a trip
The Good Day Vancouver team
If you cross the Columbia on I-5, tolls are coming into focus. A bi-state tolling subcommittee agreed on recommendations for tolls of at least $1.55 per car that would begin before construction on a replacement bridge. KATU reports drivers could start paying in summer 2028.
Toll scenarios run from $1.55 to $3.90 per trip
Sources: Camas-Washougal Post-Record, KATU
View as table
| Value | |
|---|---|
| Low end of scenarios | $1.55 |
| High end of scenarios | $3.9 |
- Pricing: rates would vary by time of day
- Estimates: given in 2026 dollars
- Final rate: still up in the air
The subcommittee's recommendations now move up to the Oregon and Washington state transportation commissions. If you want a say, watch for the public input on rate options planned for next spring or summer.
“That would be followed by final adoption of the proposal so final toll rates and policies by the end of ’27.”
Final toll rates are expected by the end of 2027
- FebruaryThe commissions take up the subcommittee's guidance.
- SpringPublic input on rate options is planned for spring or summer.
- 2027The commissions are expected to set final toll rates and policies by the end of 2027.
- Summer '28Tolling is assumed to start on the current I-5 Bridge.